VagaLune SarL Google Lunar X-prize |
Duration (days) |
Projected Start |
Projected End |
Days before Launch |
| Project Planning |
| Project Proposal |
84 |
21-Sep-07 |
14-Dec-07 |
643 |
| Internal Scheduling |
33 |
11-Nov-07 |
14-Dec-07 |
643 |
| Manufacturing contacting |
122 |
01-Mar-08 |
01-Jul-08 |
443 |
| Parts List building |
90 |
01-Feb-08 |
01-May-08 |
504 |
| LM design review |
19 |
01-Apr-08 |
20-Apr-08 |
515 |
| LM design review II |
19 |
01-Jun-08 |
20-Jun-08 |
454 |
| MR design review |
19 |
01-Mar-08 |
20-Mar-08 |
546 |
| MR design review II |
14 |
01-Jul-08 |
15-Jul-08 |
429 |
| Development & Fabrication |
| LM Comm system layout & testing |
203 |
16-Dec-07 |
06-Jul-08 |
438 |
| MR Comm system layout & testing |
207 |
16-Dec-07 |
10-Jul-08 |
434 |
| Orbital simulations |
347 |
01-Aug-08 |
14-Jul-09 |
65 |
| MR design build |
44 |
20-Jul-08 |
02-Sep-08 |
380 |
| MR range testing |
26 |
05-Sep-08 |
01-Oct-08 |
351 |
| Software Development env. setup |
19 |
01-Mar-08 |
20-Mar-08 |
546 |
| LM Assembly |
243 |
10-Jul-08 |
10-Mar-09 |
191 |
| MR Assembly |
160 |
01-Oct-08 |
10-Mar-09 |
191 |
| VagaLune Assembly+ |
60 |
02-May-09 |
01-Jul-09 |
78 |
| Launch Preparation |
| Space X contract signed & verified* |
62 |
17-Jul-08 |
17-Sep-08 |
365 |
| Structural & Design char. of payload to Space X* |
92 |
17-Aug-08 |
17-Nov-08 |
304 |
| RRTS planning* |
-- |
08 |
08 |
-- |
| Mission verification* |
16 |
01-May-09 |
17-May-09 |
123 |
| Pre-shipment review* |
10 |
05-Aug-09 |
15-Aug-09 |
33 |
| Payload to leave build facility |
3 |
25-Aug-09 |
28-Aug-09 |
20 |
| Payload arrival at RRTS* |
4 |
28-Aug-09 |
01-Sep-09 |
16 |
| Payload encapsulation* |
2 |
06-Sep-09 |
08-Sep-09 |
9 |
| Payload mate to launch vehicle* |
1 |
09-Sep-09 |
10-Sep-09 |
7 |
| Launch readiness review* |
2 |
15-Sep-09 |
17-Sep-09 |
0 |