| Launch Day Schedule |
| |
| The following table shows the approximate launch day schedule (by Space X Figure 4.8). Weather and last-minute payload modifications could alter this. |
VagaLune SarL Google Lunar X-prize |
Duration (hh:mm:ss) |
Projected Start |
Projected End |
T+hh:mm:ss |
| Launch Day |
17 September 2009, 9:00am Local Time |
| Ignition & Liftoff |
00:02:40 |
09:00:00 |
09:02:40 |
00:02:40 |
| Stage 1 Burnout/Separation |
00:00:05 |
09:02:40 |
09:02:45 |
00:02:45 |
| Stage 2 Ignition |
00:00:20 |
09:02:45 |
09:03:05 |
00:03:05 |
| Fairing Separation |
00:06:20 |
09:03:05 |
09:09:25 |
00:09:25 |
| Stage 2 Burnout |
00:00:10 |
09:09:25 |
09:09:35 |
00:09:35 |
| Payload Deployment |
00:44:44 |
09:09:35 |
09:54:19 |
00:54:19 |
| Second Burn |
00:05:41 |
09:54:19 |
10:00:00 |
01:00:00 |
|
| |
|